CONTRACTS AND PLANNING

Sample FIDIC Letters Used In Construction Industry

In this post, we are going to continue our previous post regarding FIDIC Letters, where we had listed out all the letters needed to be sent to the contractor.

Sample FIDIC Letters

All FIDIC letters shall bethat  sent to the Client or Contractor based on the scenario.

1-Engineer’s Authority to Delegate

Further to your appointment as my representative for the works, I hereby delegate to you pursuant to Clause 2.3 of the Conditions the duties and authorities vested in me under the Contract. This delegation shall take effect once a copy has been delivered to the Employer and the contractor. The clause to be delegated might be some or all of the fifty clauses where the Engineer is referred to. Delegation should not normally be considered in respect of clause 41,44,48,62,63,65,67, and 69.

2‐ Engineer’s Authority to Delegate

With reference to my letter dated ………… I hereby revoke the delegation to you of the duties and authorities made pursuant to clause 2.3 of the conditions in respect of the following clauses …………………. This revocation shall become effective when copies of this letter have been delivered to the Employer and to the Contractor. The clause to be revoked may be some or all of the clauses previously delegated.

3- Notice of Dissatisfaction with an instruction

Notice of Dissatisfaction with an instruction issued by the Engineer’s Representative We write to acknowledge receipt of your letter dated ……………………… concerning an instruction No ………………. Given by my Representative and concerning ……………… Whilst your expression of dissatisfaction has been noted I confirm the instruction as issued and give this response pursuant to Clause 2.3(b) of the conditions. In the FIDIC Letters: The engineer’s response may also be to withdraw the instruction or to vary it by issuing further instructions.

4‐ Consent to Sub‐let Date………………..

Further to your letter dated ……………… seeking permission to subcontract certain elements of the work we are writing to give our consent pursuant to Clause 4.1 of the Conditions for the following items of works to be subcontracted. Item of work Company In the FIDIC Letters: Regardless of the above consents, the Contractor will be fully responsible for any defaults of the Subcontractor as if they were caused by the contractor himself and it would be prudent for the Engineer to draw attention to this fact.

5‐ Clarification of Ambiguity

We thank you for your letter dated …………… drawing our attention to the difference between the description in the Bill of Quantities item ……….. and specification item ………… page number …………….. This is agreed and pursuant to Clause 5.2 of the Conditions we hereby instruct you to ………. In the FIDIC Letters: The Engineer may of course not accept that there is any ambiguity and will then write to give clarification if necessary and to instruct the Contractor to proceed with the works as specified.

6‐ Notice of delay in the issue of information

We thank you for your letter dated …………… and issued pursuant to Clause 6.3 of the conditions in which you have claimed that non-receipt of information is causing you delay and additional cost to the works. We have examined your program for the works which illustrates that the information referred to is not yet required and your actual progress on site is not such as to reasonably require such information to be available. Under these circumstances, we are unable to accept that your notice is a valid one. In the FIDIC Letters: Should the contractor’s notice be regarded as valid the Engineer is required to confirm this and determine the extension of time which should be granted and the amount of extra cost if any which should be added to the Contract Price.

7‐ Notice of not Foreseeable Physical Obstructions or Conditions

We acknowledge receipt of your letter dated ………….. giving notice pursuant to clause 12.2 of the Conditions of the encountering of physical obstructions in the form of …………..which in your opinion were not foreseeable by an experienced Contractor. We have carefully examined the information which was made available to you at the tender stage namely ……………..and have to advise you that we consider the matter to be one which was wholly foreseeable pursuant to Clause 12 of the conditions and have therefore to reject your notice and claim for an extension of time and additional cost.

8‐ Notice of Not Foreseeable Physical Obstruction or Conditions

I acknowledge receipt of your letter dated …………. Giving notice pursuant to Clause 12.2 of the conditions of the encountering of physical obstructions in the form of ………..which in your opinion were not foreseeable by an experienced contractor. I have examined the facts put forward by you and after my consultations with you and the Employer I have determined pursuant to Clause 12.2 that the extension of time to which you are entitled under Clause 44 shall be ………… and the amount of the costs to be added to the contract price shall be

9‐ Program to be submitted

We are writing to draw your attention to the requirement pursuant to Clause 14.1 of the Conditions to submit within the time stated in part II of the conditions a program for the works together with a method statement setting out a general description of the arrangements and methods which you are proposing for the execution of the works. The form and method of program presentation required is that set out in the tender documentation but should you require any further clarification please do not hesitate to contact me.

10‐ Setting out

We refer to your letter dated …………… in which you advise us of an error in setting out and construction as a result of incorrect data on our drawing No ……….. We, therefore, require you to rectify this error and pursuant to Clause 17.11 have determined that the amount of ………… shall be added to the Contract price in accordance with Clause 52 of the Conditions. In the FIDIC Letters: The Contractor is required to rectify any error, if required to do so by the Engineer, at his own cost unless the error is based on incorrect information or data supplied in writing by the Engineer.

11‐ Fossils

Thank you for your letter dated …………….. advising of the discovery on site of ………… Following my consultation with you and the Employer, I have determined pursuant to Clause 27.1 that the extension of time to which you shall be entitled under Clause 44 of the conditions will be ……………………. And the amount of the costs to be added to the Contract Price will be ………………

12‐ Notification of damage arising from the transport of materials or plant

Thank you for your letter dated …………….. enclosing details of a claim received from the roads (or bridges) Authority. As provided for in Clause 30.3 it is my opinion that the claim received from the Authority is due to your failure to comply with the obligations under Clause 30.1 Following my discussions with you and the Employer, I have determined that the sum recoverable from you as a result of your failure will be …………. And the amount will be deducted by the Employer from sums which may become due to you.

13‐ Facilities for other contractors

We acknowledge receipt of your letter dated ………… confirming that the following facilities …………. Have been made available to ………………. Following an examination of the detailed records that you have provided, I have determined that pursuant to Clause 31.2 the amount of …………….. should be added to the Contract price in accordance with Clause 52.

14‐ Returns of labors and Contractor’s Equipment

As previously advised, I require you to provide weekly returns of staff, labor, and plant employed on the Works and in the format discussed with you. These returns are to cover the whole of your own resources and also those of approved subcontractors and are requested pursuant to Clause 35.1 of the Conditions.

15‐ Cost of Tests not provided for

I refer to your letter dated ………….. confirming that testing has been carried out in accordance with my instruction No ……………. As these tests were not provided for in the Contract I have, after examination of records and consultations with you and the Employer determined pursuant to Clause 44 will be ……. And the amount of the costs which shall be added to the Contract price will be ……………..

16‐ Dates for Inspection and Testing

Following our agreement on the time and place for the inspection and/or testing of the ………….. I am now writing pursuant to Clause 37.3 to give you the required notice (not less than 24 hrs) of my intention to carry out the inspection/or attend the tests.

17‐ Independent Inspection

I am unable to provide the specialized equipment for the inspection and testing of …………. I am therefore in accordance with Clause 37.5 writing to give you notice that I have delegated this responsibility to ………… an independent inspector whose duties and scope of authority will be. This appointment will become effective on the ………………………… In the FIDIC Letters: No less than 14 days notice is to be given

18‐ Uncovering and making openings

I refer to my instruction to you to uncover …………….. (Or make an opening through) pursuant to Clause 38.2 of the Conditions. As the work has been found to have been executed in accordance with the Contract I have after due consultation with you and the Employer determined that ……………..representing your costs in respect of such uncovering (or making openings) reinstating and making good the same shall be added to the contract price.

19‐ Default of Contractor in compliance

I refer to my instruction ……………… and added …………………… We have agreed that the materials referred to were not in accordance with the Contract and that you are in default by not removing these within the time specified. I have therefore after consultation with you and the Employer determined pursuant to Clause 39.2 that the costs which the Employer shall be entitled to recover from you and which may be deducted by the employer from any monies due or to become due to you shall be …………..

20‐ Engineer’s Determination following suspension

Further to my instruction …………….. to you and your subsequent letter giving notice of delay and extra cost arising from my instruction I have after due consultation with you and the Employer determined pursuant to Clause 40.2 of the Conditions that the extension of time to which you shall be entitled under Clause 44 will be …………. And that the amount of cost which shall be added to the Contract Price by reason of this suspension shall be …………….

21‐ Commencement of Works

In accordance with Clause 41.1 of the Conditions, I hereby give you notice to commence the works as soon, as is reasonably possible. You are required to proceed with the works with due expedition and without delay. For the purposes of the Contract, the Commencement Date will be the receipt by you of this notice. Kindly acknowledge receipt.

22‐ Failure to give Possession

Thank you for your letter dated …………… advising that you have suffered delay and incurred costs from the failure on the part of the Employer to give possession of Site Area ……………… This has arisen due to factors beyond the Employer’s control and the matter has now been resolved. Following my consultations with you and the Employer, I have determined pursuant to Clause 42.2 that the extension of time to which you are entitled under Clause 44 shall be ………….. And that the amount of cost to be added to the Contract Price is ………………………………

23‐ Extension of time for completion

Extension of time for completion I refer to your letter dated ………………. And issued pursuant to Clause 44.2 (a) of the Conditions advising of the following event ……………….. which was such as to fairly entitle you to an extension of time for completion of the works. After my consultation with you and the employer, I have determined pursuant to Clause 44.1 that the extension of time to which you shall be entitled will be ………….. in respect of the following event In the FIDIC Letters:A similar letter pursuant to Clause 44.3 of the conditions would be issued in respect of an interim/final determination for an extension of time.

24‐ Rate of Progress

Reference is made to Site Meeting Minutes No ……….. Which sets out in detail the current progress of the works. Having considered these I give you notice that for reasons, which do not entitle you to an extension of time, the rate of progress of the works (or any Section) is in my opinion too slow to comply with the time for completion. You are therefore required to take such steps as are necessary, subject to my consent to expedite progress so as to comply with the time for completion. This notice is given as required by Clause 46.1 of the conditions and it should be noted that you shall not be entitled to any additional payment for taking such steps.

25‐ Rate of Progress

Further to my letter to you dated …………….. Requiring you to take such steps as are necessary to expedite progress I must advise you that the measures consented to will involve additional supervision costs. Following my consultation with you and the Employer regarding these, I have determined pursuant to Clause 46.1 that the additional supervision costs which shall be recoverable from you by the Employer and maybe deducted by the Employer from monies due or to become due to you amount to

26‐ Taking‐Over Certificate

We refer to your letter dated ……………….. and issued pursuant to Clause 48.1 of the conditions advising that the whole of the works have been substantially completed and have satisfactorily passed the tests on completion specified in the Contract. We are in agreement with the above and hereby certify that in our opinion the works were substantially completed in accordance with the contract on …………………… In the FIDIC Letter: The engineer may issue instructions in writing to the contractor specifying all the work which, in the Engineer’s opinion, is required to be done by the contractor before the issue of such certificate. The engineer shall also notify the contractor of any defects in the works affecting substantial completion that may appear after such instructions and before completion of the works specified therein.

27‐ Taking‐Over Certificate

We write pursuant to Clause 48.1 of the conditions to give you notice that the following items of defect have appeared in the works: Item 1 ……………………………….. Item 2 ……………………………….. These have appeared since instructions were issued to you specifying all the work which in our opinion was required to be done before the issue of a Taking‐Over Certificate. These defects will affect substantial completion.

28‐ Substantial Completion of Parts

Further to your letter dated …………….. we are now able to certify pursuant to Clause 48.3 of the conditions that the following parts of the works: 1. …………………………………. 2. …………………………………. 3. …………………………………. Have been substantially completed and have satisfactorily passed any tests on completion prescribed by the contract on ………………….. By the issue of this certificate, you are now deemed to have undertaken to complete with due expedition any outstanding work in the parts of the permanent works listed above during the defects liability period.

29‐ Cost of Remedying Defects

It has been agreed that the following items of work ……………………. Carried out after the expiration of the defects liability period is attributable to fair wear and tear. Accordingly, we have pursuant to Clause 49.3 of the conditions determined that ……………. Should be added to the contract price in accordance with Clause 52.

30‐ Contractor’s failure to Carry out Instructions

Contractor’s failure to Carry out Instructions Following your failure to carry out our instructions to remedy defects, we have after consultation with you and the Employer determined pursuant to Clause 49.4 of the Conditions that the costs which the The employer shall be entitled to recover from you and which may be deducted by the Employer from any monies that are or will become due to you are ……………………………..

31‐ Contractor to Search

We refer to the issue of an Instruction No ………………….. It is now apparent that the defect in question is one for which you are not liable under the contract. We have therefore after consultation with you and the Employer determined pursuant to Clause 50.1 of the Conditions that the amount in respect of the costs of the search carried out by you to be added to the contract price is ………………………

32‐ Variations

You are hereby instructed to carry out the works listed in the attached variation Order which is issued pursuant to Clause 51.1 of the Conditions. The effect, if any, of these variations shall be valued in accordance with Clause 52. In the FIDIC Letter: Clause 52.1, 52.2, and 52.3 require that the Engineer gives notice to the Contractor that after consultation with both the Contractor and the Employer suitable rates or prices have been agreed, and in the event of nonagreement the Engineer will determine the rates or price or such sums are to be added to the Contract Price. these notices will be copied to the Employer.

33‐ Payment of Claims

Having received from you detailed particulars of the amounts claimed and the grounds upon which your claim is based we have pursuant to Clause 53.5 of the Conditions determined that the amount in respect of your Claim No. …………… to which you are entitled to have included in interim payment Certificate No…………. will be ………………….

34‐ Works to be measured

In accordance with Clause 56.1 of the Conditions, we give notice of our requirement for the following parts of the work to be measured: ……………………………………… you are required to attend forthwith or send a qualified representative to assist in making such measurements and to supply the following particulars ………………………………… In the FIDIC Letter: Should the contractor or his representative fail to attend, then the measurement taken shall be regarded as the correct measurement of the work. Where for the purpose of measurement the Engineer has prepared records and drawings as the work proceeds he is required to give notice to the Contractor pursuant to Clause 56.1 to attend and agree on these.

35‐ Definition of “provisional Sum”

In accordance with Clause 58.1 of the conditions we have determined that the amounts to which you are entitled in respect of the work, supply or contingencies to which the following provisional sums relate are as follows: Provision Sum Ref ……………………………. Work involved: …………………………….. Amount determined: …………………………….

36‐ Certification of Payments to Nominated Subcontractor

We certify that pursuant to Clause 59.5 of the Conditions the contract has failed to provide reasonably proof that payment, less retention, included in previous certificates due to ……………………….. a the nominated subcontractor has been paid or discharged and has failed to satisfy us in writing that he has reasonable cause for withholding or refusing to make such payments or to produce to us reasonable proof that he has so informed the above-named nominated Subcontractor in writing. Accordingly, the Employer shall be entitled to pay to the above-named subcontractor directly the sum of ………………. which the contractor has failed to pay, and to deduct the amount stated from any sums due or to become due from the Employer to the Contractor. In the FIDIC Letters:The Conditions do not indicate to whom this notice should be addressed.

37‐ Final Payment Certificate

In accordance with Clause 60.8 of the Conditions we hereby certify that the amount finally due under the Contract is as follows: Final value of the works …………………………………. Less amount previously paid by Employer …………………………………. ___________________________ ………………………………….. Less sums to which the employer is entitled Under the contract (excluding liquidated Damages under Clause 47) ……………………………………. _____________________________ Balance due from the Employer to the Contractor (Or from the Contractor to the Employer)

38‐ Defects Liability Certificate

We have pleasure in certifying pursuant to Clause 62.1 of the Conditions that the date on which the contractor has completed his obligations to execute and complete the works and remedy any defects therein to our satisfaction was ……………………….

39‐ Default of Contractor

We hereby certify in accordance with Clause 63.1 of the Conditions that in our opinion the Contractor has (a) Repudiated his contract Or list other defaults under Clause 63.1 (b) – (e). In the FIDIC Letters: The Employer shall then be required pursuant to Clause 63.1 to give notice to the contractor that he will after fourteen days enter upon the site and the works and terminate the Contractor’s employment.

40‐ Valuation at date of termination

We hereby certify in accordance with Clause 63.3 of the Conditions that at the time of the Employer’s entry upon the site and termination of your employment the amount which had been reasonably earned by you or which reasonably accrue to you in respect of work than actually done by you under the contract was ……………………. And that the value of any unused or partially used materials, any contractor’s Equipment and Temporary works is ……………………. In the FIDIC Letters: The Conditions do not indicate to whom this certificate should be addressed.

41‐ Payment after Termination

We hereby certify in accordance with Clause 63.3 of the Conditions that the Employer’s costs of execution, completion and remedying of any defects, damages for delay in completion and all other expenses have amounted to ……………………………….. We hereby certify that the sum due to the Contractor upon the due completion of the contract amounts to ……………………… after the deduction of the Employer’s costs stated above. In the FIDIC Letters: The Conditions do not indicate to whom this certificate should be issued. Should there be a balance of monies due to the Employer then this is payable on demand. The Employer shall not be liable to pay the Contractor any further monies until the expiration of the defects liability period when this certificate should be issued.

42‐ Urgent Remedial Work

We write to give you notice pursuant to Clause 64.1 of the Conditions that an event of an emergency has occurred in connection with the works and in the nature of …………… This will in our opinion necessitate urgent remedial action by you for the safety of the works. In the FIDIC Letters: Should the contractor be unable or unwilling at once to do such work the Employer shall be entitled to employ others. If such work was, in the opinion of the Engineer, work for which the Contractor was liable then the Engineer shall after due consultation with the Employer and the Contractor determine the amount which shall be recoverable from the Contractor.

43‐ Damage to works by special risks

We refer to your letter dated ………………….. giving notice of damage caused by a special risk as defined in clause 20.4 of the conditions namely ……………………. Now that the damage to the works has been rectified we have pursuant to Clause 65.3 of the Conditions determined that …………………….. Should be added to the contract price in accordance with Clause 52

44‐ Increased Costs arising from Special Risks

We refer to your letter dated ………………… giving notice pursuant to Clause 65.6 of the Conditions that you have and are continuing to incur increased costs as a consequence of the occurrence of a special risk namely ………………………… After our consultation with you and the Employer, we have determined pursuant to Clause 65.5 that the amount of your costs which shall be added to the contract price will be …………………………

45‐ Outbreak of War

I am writing to give notice pursuant to Clause 65.5 that due to the outbreak of war which has materially affected the execution of the works I am with immediate effect terminating your contract.

46‐ Payment for Terminated Contract

Further to the notice of termination issued by the Employer, we have pursuant to Clause 65.8 of the Conditions determined that you shall be entitled to payment by the Employer for all work executed prior to the date of termination and in addition for all items as applicable set out in subparagraphs (a) – (f) of this Clause insofar as such amounts or items have not already been covered by payments on account to you. The provisions of the Clause shall apply and once we have all the appropriate information we shall after due consultation with you and the Employer determine any sums which are payable.

Conclusion

FIDIC letters are used on a daily basis on the sites and require in-depth knowledge however this can be used a reference only.

Tags: contract
admin

Recent Posts

How a Project Charter Can Propel Your Project to Success

Introduction: Embarking on a new project can be both exciting and daunting. With so many moving parts and stakeholders involved,…

7 months ago

Innovative Construction Recycling Project Ideas: Building a Sustainable Future

Construction Recycling Projects In the dynamic landscape of construction, sustainability is no longer an option but a necessity. As the…

7 months ago

Home Design 3D Software Review: Unleashing Creativity in Virtual Spaces

Introduction In the ever-evolving world of home design, enthusiasts and professionals alike are turning to technology to bring their visions…

10 months ago

Garden Bliss: A Guide to Beautiful and Practical Landscape Design

Introduction Landscape design is more than just creating a visually appealing outdoor space; it's about striking the perfect balance between…

11 months ago

Optimizing Reinforced Concrete Mixtures for Maximum Strength

Concrete strength is a critical factor in construction, directly influencing the durability and safety of structures. Achieving maximum strength requires…

11 months ago

Mastering Success: Essential Construction Project Management Tips for Seamless Builds

Introduction Embarking on a construction project involves intricate planning, precise execution, and effective management. As the construction industry continues to…

11 months ago

This website uses cookies.