In this post, We are going to discuss Earned Value Analysis with examples and how we can manage the finance of projects.
Cost management and control systems have a life cycle that can be defined as per the below phases. Phase 1 – Planning and Building a project price Phase 2 – Work authorization and release Phase 3 – Cost Data Collection and Reporting Phase 4 – Cost Accounting Phase 5 – Customer and Management reporting
BCWS: Budgeted Cost of Work Scheduled (Planned or Estimated) BCWP: Approved work (Earned Value. % of BCAC) ACWP: Actual Cost of Work Performed (Cost tracked from real work) BCAC: Budgeted Cost At Completion (Planned or Estimated) AQWP: Actual Quantity of Work Performed (measured at the field) BQAC: Budgeted Quantity At Completion (Planned or Estimated) ECAC: Estimated Cost At Completion
Earned value is the accepted technique for monitoring and tracking project progress. the concept of earned value revolves around these three measures. Earned Value analysis is an important subject in construction financial management and needs to be monitored properly to ensure their will be no cost overruns.
Cost and schedule variance are the two primary measures of the project progress. They can be determined by: Cost variance, CV = BCWP – ACWP
Schedule Variance, SV = BCWP -BCWS
You planned to be finished with Task A today. The scheduled cost of the task was $1,000. You have actually spent $900 to date but you are only 90% complete. What are the cost and schedule variances for Task A? CV = BCWP – ACWP = 900 – 900 = 0 SV = BCWP – BCWS = 900 – 1,000 = -100
Task is on budget but behind schedule
Two indices that are useful for communicating progress status are the Cost Performance Index and the Schedule Performance Index. They are determined by: Cost Performance Index: The cost efficiency factor represents the relationship between the actual costs expended and the value of the physical work performed. CPI = BCWP/ACWP Schedule Performance Index: The planned schedule efficiency factor represents the relationship between the value of the initial planned schedule and the value of the physical work performed. SPI = BCWP/BCWS If CPI and SPI = 1, then the project is on budget and on schedule. < 1, then the project is over budget and behind schedule. > 1, the the project is under budget and ahead of schedule
The BCWS for a task is $1,000, the ACWP is $900, and the BCWP is $900. What are the CPI and SPI for this task? CPI = BCWP/ACWP = 900/900 = 1.00 SPI = BCWP/BCWS = 900/1,000 = 0.90 Project is on budget but behind schedule.
The estimate at completion (EAC) is a projection of the final costs of work at project completion. EAC = BAC/CPI The project manager should recalculate the EAC each time project progress is measured. Budget at completion (BAC) – Original estimate of completed project costs CPI = Cost Performance Index For example, the original estimate of the project costs is $100,000. If the BCWP for the project to date is $8,000 and the ACWP is $9,300, what is the new EAC for the project? CPI = BCWP/ACWP = 8,000/9,300 = 0.86 For example the original estimate of the project costs is $100,000. If the BCWP for the project to date is $8,000 and the ACWP is $9,300, what is the new EAC for the project? Solution: CPI = BCWP/ACWP = 8,000/9,300 = 0.86
Estimate to Complete (ETC) or the amount of money needed to fund the project to completion is calculated by: ETC = EAC-ACWP
In conclusion, Earned Value Analysis is a powerful project management tool that enables project managers to track project performance against a set baseline. By measuring both the schedule and cost performance of a project, project managers can identify potential issues early on and take corrective action to keep the project on track. While implementing Earned Value Analysis can be complex and time-consuming, the benefits in terms of improved project performance and cost control make it well worth the effort. With careful planning and execution, project managers can use Earned Value Analysis to achieve project success.
Introduction: Embarking on a new project can be both exciting and daunting. With so many moving parts and stakeholders involved,…
Construction Recycling Projects In the dynamic landscape of construction, sustainability is no longer an option but a necessity. As the…
Introduction In the ever-evolving world of home design, enthusiasts and professionals alike are turning to technology to bring their visions…
Introduction Landscape design is more than just creating a visually appealing outdoor space; it's about striking the perfect balance between…
Concrete strength is a critical factor in construction, directly influencing the durability and safety of structures. Achieving maximum strength requires…
Introduction Embarking on a construction project involves intricate planning, precise execution, and effective management. As the construction industry continues to…
This website uses cookies.